Hollisand Builders is invented: a commercial general contractor with nine jobs and sample books. Its reports tie to each other the way real ones must, and to the construction dashboard on the home page. No figure here comes from a client.
Revenue $112,300 over budget. Both the warehouse expansion and the school addition earned ahead of schedule on cost to cost.
Subcontractors $71,400 over. Most of it is the fire station's concrete and steel, forecast $420,000 over bid across the job.
Field labor $29,200 over. Overtime was 5.4% of field hours, mostly concrete finishers chasing pours.
Other job costs $12,000 under. Fewer small tools and dumpster pulls than planned.
Net income $250,000, $4,000 under budget and ahead of last September by $32,800. Year to date: $1,642,000.
Balance sheet
Hollisand Builders
At 30 September 2026, against 31 December 2025
Sample company, sample data
30 Sep 2026
31 Dec 2025
Current assets
Cash
3,512,000
3,960,000
Contract receivables, less retention
4,348,000
4,120,000
Retention receivable
2,883,000
2,410,000
Costs and estimated earnings in excess of billings
850,712
412,000
Prepaid expenses
188,000
162,000
Property and equipment, net
1,284,000
1,340,000
Other assets
412,000
398,000
Total assets
13,477,712
12,802,000
Liabilities
Accounts payable, less retention
2,306,000
2,480,000
Retention payable
1,815,000
1,360,000
Billings in excess of costs and estimated earnings
979,517
1,140,000
Accrued payroll, taxes and other
393,195
254,000
Equipment notes
742,000
918,000
Total liabilities
6,235,712
6,152,000
Members' equity
7,242,000
6,650,000
Total liabilities and equity
13,477,712
12,802,000
Commentary
Ties out. Over billings $979,517 and under billings $850,712 are the WIP schedule's totals. Receivables $4,348,000 is the aging's total. Retention matches the job ledger both ways.
Equity moved from $6,650,000 by $1,642,000 of net income less $1,050,000 of distributions.
Working capital is $6,288,000, current assets less current liabilities.
13-week cash flow
Hollisand Builders
From the week of Oct 19, starting cash $3,840,000
Sample company, sample data
Ending cash
Lowest week
Floor, $2.0M
Week of
Starting
Pay applications in
Subs and suppliers
Payroll
Overhead and debt
Ending
Oct 19
3,840,000
1,210,000
(1,020,000)
(268,000)
(92,000)
3,670,000
Oct 26
3,670,000
1,640,000
(1,198,000)
0
(92,000)
4,020,000
Nov 2
4,020,000
980,000
(1,100,000)
(268,000)
(92,000)
3,540,000
Nov 9
3,540,000
1,420,000
(1,118,000)
0
(92,000)
3,750,000
Nov 16
3,750,000
1,580,000
(1,280,000)
(268,000)
(92,000)
3,690,000
Nov 23
3,690,000
1,110,000
(1,298,000)
0
(92,000)
3,410,000
Nov 30
3,410,000
1,690,000
(950,000)
(268,000)
(92,000)
3,790,000
Dec 7
3,790,000
860,000
(1,428,000)
0
(92,000)
3,130,000
Dec 14
3,130,000
1,520,000
(920,000)
(268,000)
(92,000)
3,370,000
Dec 21
3,370,000
1,380,000
(1,378,000)
0
(92,000)
3,280,000
Dec 28
3,280,000
610,000
(720,000)
(268,000)
(92,000)
2,810,000
Jan 4
2,810,000
1,740,000
(1,268,000)
0
(92,000)
3,190,000
Jan 11
3,190,000
1,460,000
(1,050,000)
(268,000)
(92,000)
3,240,000
13 weeks
3,840,000
17,200,000
(14,728,000)
(1,876,000)
(1,196,000)
3,240,000
Commentary
Lowest week: Dec 28, $2,810,000, $810,000 above the floor agreed with the bank.
Pay applications in are the amounts due under each contract, less retention, timed on each owner's paying history.
Receivables and payables aging
Hollisand Builders
At 30 September 2026, retention shown on the balance sheet
Sample company, sample data
Receivables by job
Current
1 to 30
31 to 60
61 to 90
Over 90
Total
J-2401 Harbor medical office building
668,000
260,000
120,000
0
0
1,048,000
J-2403 Riverside self-storage
200,000
120,000
60,000
38,000
0
418,000
J-2405 Fire station 7
430,000
180,000
92,000
0
0
702,000
J-2407 Oakmont retail center
210,000
110,000
0
0
64,000
384,000
J-2408 Elementary school addition
516,000
210,000
90,000
80,000
0
896,000
J-2409 Dental clinic build-out
102,000
40,000
0
0
0
142,000
J-2410 Credit union branch
156,000
30,000
50,000
0
0
236,000
J-2411 Warehouse expansion
374,000
30,000
0
0
0
404,000
J-2412 Church fellowship hall
118,000
0
0
0
0
118,000
Total
2,774,000
980,000
412,000
118,000
64,000
4,348,000
Payables by trade
Current
1 to 30
31 to 60
61 to 90
Over 90
Total
Concrete subcontractors
272,000
180,000
60,000
0
0
512,000
Steel fabricator and erector
218,000
150,000
70,000
0
0
438,000
Mechanical, plumbing and electrical subs
334,000
230,000
40,000
20,000
0
624,000
Material suppliers
204,000
140,000
24,000
18,000
0
386,000
Equipment rental
82,000
56,000
10,000
0
0
148,000
Other vendors
138,000
50,000
10,000
0
0
198,000
Total
1,248,000
806,000
214,000
38,000
0
2,306,000
Commentary
$64,000 over 90 days is one change order on the Oakmont retail center, approved in the field and not yet signed by the owner.
Payables over 60 days, $38,000, are held against punch-list items on two subcontracts.
Work in progress schedule
Hollisand Builders
At 30 September 2026, percent complete by cost to cost
Sample company, sample data
Job
Contract
Est. cost
Est. gross profit
Cost to date
Complete
Earned
Billed
Over (under)
Backlog
J-2401 Harbor medical office building
14,850,000
13,215,000
1,635,000
11,890,000
90%
13,361,067
13,520,000
158,933
1,488,933
J-2403 Riverside self-storage
6,420,000
5,650,000
770,000
5,105,000
90%
5,800,726
5,640,000
(160,726)
619,274
J-2405 Fire station 7
8,960,000
8,310,000
650,000
4,120,000
50%
4,442,262
4,880,000
437,738
4,517,738
J-2407 Oakmont retail center
5,380,000
4,760,000
620,000
2,950,000
62%
3,334,244
3,050,000
(284,244)
2,045,756
J-2408 Elementary school addition
11,240,000
10,170,000
1,070,000
6,330,000
62%
6,995,988
6,710,000
(285,988)
4,244,012
J-2409 Dental clinic build-out
1,860,000
1,610,000
250,000
1,402,000
87%
1,619,702
1,560,000
(59,702)
240,298
J-2410 Credit union branch
3,270,000
2,880,000
390,000
1,145,000
40%
1,300,052
1,240,000
(60,052)
1,969,948
J-2411 Warehouse expansion
7,680,000
6,950,000
730,000
1,610,000
23%
1,779,108
2,120,000
340,892
5,900,892
J-2412 Church fellowship hall
2,940,000
2,610,000
330,000
380,000
15%
428,046
470,000
41,954
2,511,954
Nine jobs
62,600,000
56,155,000
6,445,000
34,932,000
62%
39,061,195
39,190,000
128,805
23,538,805
Commentary
Over billings $979,517, under billings $850,712. Both carry to the balance sheet as they stand.
Estimated gross profit 10.3% against 11.0% at bid. Fire station 7 accounts for most of the fade.
Backlog $23,538,805, about 4.3 months of September's revenue.
Job cost report, J-2405 Fire station 7
Hollisand Builders
At 30 September 2026. Contract $8,960,000, 50% complete
Sample company, sample data
Forecast at completion
Cost to date
Budget at bid
Phase
Budget
Committed
Cost to date
Cost to complete
Forecast
Over (under)
General conditions
742,000
380,000
361,000
429,000
790,000
48,000
Sitework
618,000
640,000
604,000
48,000
652,000
34,000
Concrete
1,046,000
1,102,000
1,018,000
110,000
1,128,000
82,000
Structural steel
884,000
948,000
786,000
176,000
962,000
78,000
Masonry
712,000
698,000
402,000
306,000
708,000
(4,000)
Roofing
396,000
404,000
96,000
308,000
404,000
8,000
Mechanical and plumbing
1,486,000
1,492,000
418,000
1,124,000
1,542,000
56,000
Electrical
1,018,000
1,046,000
296,000
764,000
1,060,000
42,000
Interiors and finishes
988,000
940,000
139,000
925,000
1,064,000
76,000
Job
7,890,000
7,650,000
4,120,000
4,190,000
8,310,000
420,000
Commentary
Forecast $8,310,000 against a $7,890,000 budget: gross profit falls from 11.9% at bid to 7.3%.
Cost to date $4,120,000 is the WIP schedule's cost to date for this job, line for line.
Payroll and labor
Hollisand Builders
September 2026, field payroll
Sample company, sample data
Labor share of revenue
Field labor, share of revenue
Target 13%
Craft
People
Hours
Overtime
OT share
Wages
Burden
Labor cost
Carpenters
32
5,376
320
5.6%
181,536
57,187
238,723
Laborers
28
4,704
260
5.2%
117,162
36,908
154,070
Concrete finishers
12
2,016
180
8.2%
64,008
20,164
84,172
Equipment operators
8
1,344
96
6.7%
50,592
15,937
66,529
Superintendents
9
1,512
0
0.0%
142,740
44,966
187,706
Field
89
14,952
856
5.4%
556,038
175,162
731,200
Commentary
Field labor cost $731,200, 13.5% of revenue. It is the P&L's field labor line to the dollar.
Burden 31.5% of wages: payroll taxes, workers' compensation, health and retirement.
KPI scorecard
Hollisand Builders
September 2026
Sample company, sample data
Measure
Target
Actual
Status
Trend
Revenue, September
$5,300,000
$5,412,300
✓On track
Gross margin
12.0%
11.6%
◆Watch
Net income
$254,000
$250,000
◆Watch
Estimated gross profit in WIP
11.0% at bid
10.3%
◆Watch
Backlog, months of revenue
5.0
4.3
◆Watch
Net over billings
Above zero
$129K
✓On track
Cash, lowest of 13 weeks
Over $2.0M
$2.81M
✓On track
Receivable days, retention aside
Under 35
24
✓On track
Field labor, share of revenue
13.0%
13.5%
◆Watch
Overtime, share of field hours
Under 5%
5.4%
◆Watch
Commentary
4 on track, 6 to watch, 0 off target. Most of the watch list traces to one job: the fire station's fade, and the overtime spent catching it up.
Board pack
Hollisand Builders
September 2026, for the meeting of Thu 22 Oct
Sample company, sample data
Revenue$5.41M$112K over budget
Net income$250K$1.64M year to date
Backlog$23.5M4.3 months of revenue
Cash$3.51Mlowest ahead $2.81M
The month in four sentences
Revenue beat budget and gross profit missed it, because the fire station's concrete and steel are running over bid. The other eight jobs are within a point of their bid margins. Billings are $129K ahead of the work across the company, and cash stays above the floor all quarter. Up for decision: whether to claim a change order for the fire station's concrete overrun, on page 6.